Category:
Transportation
Client:
Ministry of Public Works and Transport
Region:
Jiyeh
Starting Date:
2010
Completion Date:
2011
Details:
Design review, technico-economic-study for the development of the port and supervision of the construction of the new fishing port breakwaters and basin.
The main breakwater is 360 m in length and is protected by a layer of 12m3 concrete Acropodes. Large rock blocks up to 10 tons and Acropodes 6.3m3 are also used in the construction of the breakwaters. The service capacity of the port can reach more than 150 small crafts.
300km of Sewers Within Nabatiyeh & South Lebanon Mohafazats
The master plan required covered the southern part of the country namely both … »
Lebanon Water and Wastewater Sector Support Program (LWPP)
In 2010, USAID commissioned Development Alternatives Inc. (DAI) with the implementation of the … »
Evaluation of Fixed Assets in BMLWE
In 2010, the Etablissement des Eaux de Beyrouth et du Mont Liban (EBML/BMLWE) … »
Preliminary and Detailed Design for Younine Dam
The Younine Plateau is located 3 km North-East of Baalbeck in the Anti-Lebanon … »