Jiyeh

»  Jiyeh Fishing Port Details

Category:

Transportation

Client:

Ministry of Public Works and Transport

Region:

Jiyeh

Starting Date:

2010

Completion Date:

2011

Details:

Design review, technico-economic-study for the development of the port and supervision of the construction of the new fishing port breakwaters and basin.

The main breakwater is 360 m in length and is protected by a layer of 12m3 concrete Acropodes. Large rock blocks up to 10 tons and Acropodes 6.3m3 are also used in the construction of the breakwaters. The service capacity of the port can reach more than 150 small crafts.

 

«   BACK

»  OTHER PROJECTS

Water Network Design for Upper Baabda Villages

In 2011, the Etablissement des Eaux to Beyrouth et du Mont Liban (EBML) … »

Drinking Water Network and Sewerage System of Ehden

In 2007, the Council for Development & Reconstruction commissioned Kredo with the Supervision … »

Conveying of Antelias Grotto Water Sources to Dbayeh Treatment Plant

The project consists of building an underground diversion dam and intake structure inside … »

Dekwaneh Bridge for New Grade Separation at Dekwaneh Square

Design of an overpass with two lanes of a 600m long prestressed concrete … »

Road Network Maintenance in the Caza of Zahlé

The length of the road network within the Caza of Zahlé is around … »