»  Rehabilitation of the Bared Main Irrigation Channel – Akkar Details

Category:

Hydraulics and Rural Development

Sub-Category:

Channels, Irrigation networks

Client:

Etablissement des Eaux du Liban Nord

Region:

Akkar

Starting Date:

2009

Completion Date:

Ongoing

Details:

The Bared main irrigation channel in Akkar runs over 13 km from the Bared diversion dam to the Arqa river, it irrigates a large area in the Akkar plain. The Etablissement des Eaux du Liban Nord has commissioned KREDO with the design for rehabilitation and supervision of works for this channel which includes 3 tunnels and one arch bridge aqueduct as well as multiple siphons and road crossings.

The project is funded by the EU.

«   BACK

»  OTHER PROJECTS

Supervision of Nabatiyeh – Doueir Road

In January 2009, the Ministry of Public Works and Transport commissioned Kredo with … »

Evaluation of Fixed Assets in BMLWE

In 2010, the Etablissement des Eaux de Beyrouth et du Mont Liban (EBML/BMLWE) … »

Drinking Water Network and Sewerage System of Ehden

In 2007, the Council for Development & Reconstruction commissioned Kredo with the Supervision … »

Collection and Piping (Captage) of Chaqha Springs in Mydaneh Plain

Mydaneh plain falls in the neighborhood of Kfarrouman village to the east of … »

Meknes (Morocco) Wastewater Reuse

USAID has commissioned the Advancing the Blue Revolution Initiative (ABRI), managed by Development … »