Category:
Transportation
Client:
Ministry of Public Works and Transport
Region:
South Lebanon
Starting Date:
2001
Completion Date:
2002
Details:
In line with the policy implemented by the Ministry of Public Works and Transport to upgrade all major roads with street lighting, street lighting network on Zahrani – Tyre international road (10km) and the Joaya – Tebnine road (30km) were equipped with a street lighting network.
The supervision tasks involved approval of the lighting materials proposed by the contractor (cables, poles, luminaries, control boards, photo cells, transformers…), location and laying of cables, construction of manholes, erection of poles, and installation of luminaires, boards, transformers… etc., as well as the testing of each element and the system as a whole.
A GIS compatible data base and plans were also prepared.
Preliminary and Detailed Design for Younine Dam
The Younine Plateau is located 3 km North-East of Baalbeck in the Anti-Lebanon … »
Sewage Networks in El Mari and EL Fardis & Surface Drainage Channels in Kfarhamam
Population survey and data collection for existing wastewater facilities in Caza Hasbaya. Identifying … »
Road Network Classification in Mohafazats of Bekaa and Baalbeck El Hermel
Using the most recent satellite photos to locate and identify the network of … »
Conveying of Antelias Grotto Water Sources to Dbayeh Treatment Plant
The project consists of building an underground diversion dam and intake structure inside … »
Upgrade of Roundabout at Dekwaneh Square
Design of a 60m diameter roundabout connecting seven arms of the intersection in … »