National Roads Program Second Year Lot 1 Rehabilitation Design

Within the framework of the World Bank funded National Road Program (NRP) Kredo in association with Tecsult Int. Ltd. of Montreal, was commissioned with the full rehabilitation study for the primary connection:

PRI 003           Al Abdeh – Berqayel – Fnaydeq         42km

The study included the following tasks:

Road condition survey and analysis, Identification of optimal rehabilitation strategy, Topographical survey, Geotechnical investigations, Hydrological Survey, Environmental Impact Assessment, Traffic survey, Pavement Design, Review and Adjustment of road geometry and profiles, Structural Design of Retaining Walls and Hydraulic Structures, Preparation of Construction Drawings and Tender Documents, Construction cost estimate, Expropriation plans and documents, as well as Economic Analysis on HDM-4.

«   BACK

»  OTHER PROJECTS

Meknes (Morocco) Wastewater Reuse

USAID has commissioned the Advancing the Blue Revolution Initiative (ABRI), managed by Development … »

Minieh Roads and Coastal Boulevard and Port

The development of the coastal town of Minieh in North Lebanon requires the … »

Wehbe Building – Sassine Square

WehbeBuilding is an existing building on Sassine Square. The Client wanted to excavate … »

Supervision of Iklim Kharoub Roads, Lebanon

In 2007, the Council for Development & Reconstruction commissioned Kredo with the Supervision … »

Drinking Water Network and Sewerage System of Ehden

In 2007, the Council for Development & Reconstruction commissioned Kredo with the Supervision … »